[1] The following diagram explains the ideal environment for running the Digi-CA™ Server Xs single server system. The Strong Room/locked server cabinet should be a secured with biometric access, ideally with main power supply and a backup power supply with at least one reliable internet connection. Access to this area should be restricted to Administrators only. Two trusted and approved Administrators should be present at all times when the area is being accessed.
[1] The following technical installation diagram outlines the typical network requirement to run and operate a single server Digi-CA™ Server Xs system without a HSM. Backup server is optional.
[1] The following is the time required to install a single server Digi-CA™ Server Xs system without a HSM. Backup server is optional.
Days Project Part Persons Description
0.5 Server Configurations
0.5 RA Core configuration, Digi-CA™, RA and Public services configuration
0.5 Network connectivity and service accessibility tests
0.5 Root and Intermediate CA Key Ceremony
0.5 Digi-CA™ Administration Training
0.5 RA Training
3 Total Project Installation Time
Note: This installation can be conducted by two personnel, a qualified IT person and a Network Engineer. Alternatively, Digi-CAST2™ can conduct the installation and in some cases this can occur from outside the environment using virtual access (this means there is no on site visit required).
[1] The following is the time required to install a single server Digi-CA™ Server Xs system with a HSM. Backup server is optional.
Days Project Part Persons Description
0.5 Server Configurations
0.5 Digi-CA™ Core configurations
0.5 Digi-CA™ RA and Public services configuration
1 HSM configuration
0.5 Network connectivity and service accessibility tests
0.5 Root and Intermediate CA Key Ceremony
0.5 Digi-CA™ Administration Training
0.5 RA Training
4.5 Total Project Installation Time
[1] The following technical installation diagram outlines the typical network requirement to run and operate a single server Digi-CA™ Server Xs system with a HSM. Backup server is optional.
[1] The following diagram explains the ideal environment for running the dual server Digi-CA™ Server Xp system. The Strong Room/locked server cabinet should be a secured with biometric access, ideally with two power supplies and two separate internet connections from two different providers. Access to this area should be restricted to Administrators only. Two trusted and approved Administrators should be present at all times when the area is being accessed.
[1] The following technical installation diagram outlines a typical network requirement to run and operate a dual server Digi-CA™ Server Xp system without a HSM. Backup server is optional.
[1] The following is the time required to install a dual server Digi-CA™ Xp system without a HSM. Backup server is optional.
Days Project Part Persons Description
1 Server Configuration
1 RA Core configuration
1 Digi-CA™ Server Failover and Database Replication configuration
1 Digi-CA™ RA and Public services configuration
0.5 Digi-CA™ RA and Public services redundancy configuration
1 Network connectivity and service accessibility tests
0.5 Root and Intermediate CA Key Ceremony
0.5 Digi-CA™ Administration Training
0.5 RA Training
7 Total Project Installation Time
[1] The following technical installation diagram outlines a typical network requirement to run and operate a dual server Digi-CA™ Server Xp system with a HSM. Backup server is optional.
[1] The following is the time required to install a dual server Digi-CA™ Server Xp system with a HSM. Backup server is optional.
Days Project Part Persons Description
1 Server Configuration
1 Digi-CA™ Core configuration
1 Digi-CA™ Server Failover and Database Replication
1 Digi-CA™ RA and Public services configuration
0.5 Digi-CA™ RA and Public services redundancy configuration
1 HSM configuration
1 Network connectivity and service accessibility tests
0.5 Root and Intermediate CA Key Ceremony
0.5 Digi-CA™ Administration Training
0.5 RA Training
8 Total Project Installation Time
[1] The following technical installation diagram outlines a typical network requirement to run and operate a multi-server Digi-CA™ Server Xg, full redundancy system with a HSM and optional HSM Fail Over (not shown).`
[1] The following is the time required to install a multi-server Digi-CA™ Server Xg full redundancy system with an HSM.
Days Project Part Persons Description
2 Server Configuration
1 Digi-CA™ Core configuration
1 Digi-CA™ Server Failover and Replication
1 Digi-CA™ RA and Public services configuration
0.5 Digi-CA™ RA and Public services redundancy configuration
1 HSM configuration
1 Network connectivity and service accessibility tests
0.5 Root and Intermediate CA Key Ceremony
0.5 Digi-CA™ Administration Training
0.5 RA Training
9 Total Project Installation Time